Why does a project team schedule checkpoints during execution?
To compare progress with the plan and decide how to respond.
- To replace every original goal
- To compare progress with the plan ✔
- To postpone all difficult decisions
Why: Real work rarely follows a plan perfectly. At checkpoints, the team spots gaps early and chooses adjustments that still support the project objectives.
Huh, didn't know that: Staff meetings, inspections, schedules, and budget reviews can all serve as checkpoints.
Why did the checklist feel important? Everyone kept checking it out.
Like this card?
References
Answer: To compare progress with the plan. Real work rarely follows a plan perfectly. At checkpoints, the team spots gaps early and chooses adjustments that still support the project objectives.
- Learn to Lead, Volume 3 www.gocivilairpatrol.com/media/cms/L2LVolume_3__LOW_FINAL_4_MAY_13CC68236BDFE.pdf
Project managers establish checkpoints, predetermined moments where the team asks, What is going according to plan?
Checked 2026-10-10.
Think this answer is wrong? Tap "Challenge this answer" on the card in the game and tell us why.