In the built Hyatt Regency walkway system, what supported the second-floor walkway?

It hung from the fourth-floor walkway.

Start playing free

  1. Only the atrium floor
  2. The fourth-floor walkway ✔
  3. The third-floor walkway

Why: The changed hanger arrangement made the fourth-floor connection carry load from both stacked walkways. The case teaches that a shop-detail change can alter the load path and demands full engineering review.

Huh, didn't know that: The National Bureau of Standards investigation combined site inspection, laboratory testing, and structural analysis.

The dad joke
Structural drawings need support from careful review.
Like this card?
Play the game

References

Answer: The fourth-floor walkway. The changed hanger arrangement made the fourth-floor connection carry load from both stacked walkways. The case teaches that a shop-detail change can alter the load path and demands full engineering review.

  1. NIST FireDOC, Investigation of the Kansas City Hyatt Regency Walkways Collapse firedoc.nist.gov/article/t3cyXYQBWEcjUZEYe498
    The second floor walkway was suspended from the forth floor walkway which was directly above it.
    Checked 2026-10-10.