In the built Hyatt Regency walkway system, what supported the second-floor walkway?
It hung from the fourth-floor walkway.
- Only the atrium floor
- The fourth-floor walkway ✔
- The third-floor walkway
Why: The changed hanger arrangement made the fourth-floor connection carry load from both stacked walkways. The case teaches that a shop-detail change can alter the load path and demands full engineering review.
Huh, didn't know that: The National Bureau of Standards investigation combined site inspection, laboratory testing, and structural analysis.
Structural drawings need support from careful review.
References
Answer: The fourth-floor walkway. The changed hanger arrangement made the fourth-floor connection carry load from both stacked walkways. The case teaches that a shop-detail change can alter the load path and demands full engineering review.
- NIST FireDOC, Investigation of the Kansas City Hyatt Regency Walkways Collapse firedoc.nist.gov/article/t3cyXYQBWEcjUZEYe498
The second floor walkway was suspended from the forth floor walkway which was directly above it.
Checked 2026-10-10.